cleanup · Niagara County

Durez / Occidental Chemical

North Tonawanda

Historic chemical-manufacturing property near Walck and River roads. The closed Class 4 State Superfund site remains under management; DEC's sediment inventory identifies adjacent sediment affected by chlorinated dioxins and furans. The facility, groundwater, outfalls, and sediment require separate but connected interpretation.

The documented story

What happened here?

Harry M. Dent founded General Plastics, Inc. on the North Tonawanda property in 1921. The business adopted the Durez Plastic and Chemical Company name in 1926 and developed into a major producer of phenolic resins and molding compounds.

Phenol and formaldehyde were the principal raw materials for thermosetting resins and molding powders used in electrical, automotive, appliance, communications, and industrial components. The Durez name became closely associated with durable molded phenolic plastic before newer polymer families displaced many of those applications.

Durez joined Hooker Chemical in the mid-1950s and became part of Occidental when Occidental acquired Hooker in 1968. Occidental gradually reduced operations during the late 1980s and early 1990s; manufacturing ended in 1995 and plant demolition was completed in December 1997.

The environmental record is divided among the former plant, buried or spilled material, groundwater, the Pettit Cove Flume, Pettit Cove, and Niagara River sediment. Treating all of those areas as one uniform deposit would obscure both the history and remedy.

Pettit Creek was converted into a covered storm-drain system before the mature Durez era. Historical newspaper images preserved by North Tonawanda History record basement explosions associated with gas in the flume in 1949 and a fish kill involving hundreds of fish in 1953. These accounts establish what people observed and what local reporting said at the time; later sampling provides the evidence for particular contaminants and sources.

Plastics innovation, neighborhood concern, and cleanup

A celebrated local product left a complicated community inheritance

1921-1995local plastics and chemical manufacturing era

1921 onward

Durez connected local work to products used nationwide

Harry M. Dent founded General Plastics before the company adopted the Durez name. Phenolic resins and molding compounds supplied electrical, automobile, appliance, communications, and industrial products, leaving advertising, employee badges, and product history in North Tonawanda archives.

Late twentieth century

Residents organized around what moved beyond the plant

Investigations examined the former plant and off-site pathways including Pettit Cove Flume and Niagara River sediment. The Durez Area Community Residents organization formed in response to concern about chemicals around the property and became part of the Love Canal-era regional archive.

1995-present

Production ended while treatment continued

Manufacturing stopped in 1995 and buildings were demolished, but groundwater interception, carbon treatment, covers, monitoring, and maintenance continued. Closure of the factory therefore did not end either the remedy or the community's historical relationship with the site.

North Tonawanda History: Durez collectionNYSDEC: Region 9 Durez project summaryUniversity at Buffalo: Love Canal archive glossaryNYSDEC: 1989 Durez remedy decision

News record

Major news events

Coverage selected here marks a turning point in public awareness, policy, enforcement, employment, or cleanup. Links open at the original publisher or archive; WNYAtlas does not reproduce restricted articles or images.

Local

Gas in the enclosed Pettit Creek system is linked to basement explosions

The North Tonawanda History collection preserves a contemporary Tonawanda News article about emergency response to explosions associated with gas in the covered flume. It documents the event and contemporary explanation; it does not by itself establish the complete chemical source profile later developed by investigators.

North Tonawanda History / Tonawanda News archive
Local

Hundreds of fish die in a documented Pettit Flume pollution event

A preserved local-news image records a visible ecological consequence during the Durez operating era, decades before the later dioxin, sediment-removal, and biomonitoring programs.

North Tonawanda History / Tonawanda News archive
Regional

Post-remedy mussel and sediment monitoring continues to detect Durez-pattern dioxins and furans

Binational Niagara River reports documented continuing bioavailability after major removals, maintenance dredging in 2000, and additional monitoring rather than treating construction completion as the end of the environmental record.

Niagara River Toxics Management Plan

Chemical guide

Chemicals named in this record

These links explain potential hazards and exposure pathways. A chemical named in a record does not establish that anyone was exposed or harmed.

Chronology

Timeline

  1. 1921

    Harry M. Dent founded General Plastics, Inc. at the future Durez property.

  2. 1926

    The company became Durez Plastic and Chemical Company and expanded phenolic-resin and molding-compound production.

  3. 1949-1953

    Local reporting documented basement explosions associated with gas in the covered flume and a later fish kill involving hundreds of fish during the plant's operating period.

  4. Mid-1950s-1968

    Durez joined Hooker Chemical and later became part of Occidental through Occidental's acquisition of Hooker.

  5. 1977 onward

    Occidental and DEC began formal source-control, investigation, and remedial work at and around the facility.

  6. 1989

    A partial consent judgment established major groundwater-monitoring and remediation obligations.

  7. Late 1980s-1997

    Operations were gradually reduced, manufacturing ended in 1995, and demolition of the former plant buildings was completed in 1997.

  8. 1997-2006

    Post-remedy sediment and caged-mussel monitoring continued to find Durez-pattern dioxins and furans in Pettit Cove; maintenance dredging removed about 400 additional cubic yards in 2000 and monitoring continued.

  9. 1998-present

    Glenn Springs Holdings assumed long-term remedial responsibility, operating the interceptor trench, carbon treatment, monitoring, and maintenance program.

  10. 2019-2024

    Targeted in-well oxygen-release treatment and updated groundwater studies evaluated persistent chlorinated compounds and hydraulic capture.

  11. Current stewardship

    Groundwater levels, chemistry, hydraulic capture, sediment conditions, and engineering controls remain subject to monitoring and review.

Environmental record

Documented impacts

  • Burial areas, process losses, and spills affected surface soil, subsurface soil, and groundwater beneath portions of the former manufacturing property.
  • The groundwater program tracks benzene, toluene, chlorobenzene, dichlorobenzenes, and trichlorobenzenes among the targeted site compounds.
  • Until 1993, non-contact cooling water and stormwater entered the Pettit Cove Flume. Investigations identified chlorinated dioxins and furans in flume, cove, and connected river sediments potentially associated with historical facility discharges.
  • The principal remedial program removed approximately 25,000 cubic yards of contaminated sewer and cove sediment. Later monitoring found contamination in newly deposited material and demonstrated that dioxins and furans remained available to aquatic organisms, showing why removal totals alone do not establish that a pathway has ended.
  • NAPL can enter the interceptor trench with groundwater and is separated for off-site incineration. Its presence shows why hydraulic collection remains necessary decades after manufacturing ended.
  • The long operating history produced multiple source, drainage, and sediment areas rather than a single uniform deposit.

Response

Cleanup and controls

  • A perimeter interceptor trench creates an inward hydraulic gradient and collects groundwater that might otherwise migrate away from the property.
  • Collected water passes through separation equipment and an activated-carbon treatment system before permitted discharge; separated NAPL is sent to a permitted off-site incinerator.
  • Source removals, plant demolition, site covers, drainage work, sediment removal, and long-term groundwater management address different parts of the former operation.
  • Institutional controls, monitoring wells, sediment restrictions, maintenance, hydraulic evaluation, and periodic review remain essential because contamination has not simply been excavated away.

Then and now

The site today

The manufacturing complex is gone and the former plant is largely open land, but the interceptor trench and treatment plant operate continuously as part of a managed Class 4 State Superfund remedy.

The correct present-day description is neither an uncontrolled historic dump nor a completely erased cleanup: groundwater capture, sediment review, and continuing controls are integral parts of the remedy.