radiological · Erie County

Ashland 1 / Former Ashland Oil Refinery

Town of Tonawanda

Former River Road refinery property where Linde uranium-processing residues had been stored before Ashland Oil acquired the land; federal cleanup was completed in 2003.

The documented story

What happened here?

Ashland 1, historically known as the Haist Property, stored about 8,000 tons of low-grade uranium-ore tailings from Linde's Manhattan Project-era processing between 1944 and 1946. Ashland Oil later acquired the land in 1960 and incorporated it into refinery operations.

The property is part of the interconnected Tonawanda FUSRAP story: material originated at Linde, was stored at Ashland 1, and some was later moved to Seaway. The federal remedy removed qualifying radiological material rather than treating every consequence of later refinery use as a FUSRAP condition.

Wartime uranium residues entered a later refinery landscape

Ashland 1 carried material from Linde's uranium program into Tonawanda's postwar industrial era

173,000 tonsmaterial excavated during the completed Ashland 1 cleanup

1944-1946

A storage property became part of the Manhattan Project supply chain

Linde processed uranium ore in Tonawanda for the wartime atomic program. Roughly 8,000 tons of low-grade tailings were placed at the property then known as the Haist site, linking this River Road parcel to production performed elsewhere.

1960-1974

A refinery inherited the land and later moved some affected soil

Ashland Oil acquired the property in 1960 for refinery use. During 1974 drainage-ditch and tank-berm construction, radioactive residue mixed with excavated soil was transported to Ashland 2 and Seaway, extending one historical material chain across multiple properties.

1998-2006

Federal cleanup removed the residue instead of containing it in place

The Army Corps selected excavation and off-site disposal. Cleanup at Ashland 1 was completed in 2003 after approximately 173,000 tons were removed; related work at Rattlesnake Creek concluded in 2005 and the Ashland completion report followed in 2006.

U.S. Army Corps: Ashland 1 FUSRAP siteDOE Legacy Management: Tonawanda North Unit 1DOE: Tonawanda FUSRAP stakeholder report

Manhattan Project-derived material: wartime Linde residues stored on the property

News record

Major news events

Coverage selected here marks a turning point in public awareness, policy, enforcement, employment, or cleanup. Links open at the original publisher or archive; WNYAtlas does not reproduce restricted articles or images.

Regional

Wartime residues are stored, then moved among Tonawanda industrial properties

Material originating with Linde uranium processing remained at Ashland 1 before later transfers spread part of the cleanup responsibility to Ashland 2 and Seaway Area D.

U.S. Army Corps of Engineers
Local

Public information sessions accompany removal and federal closeout

The federal community-relations record documents information repositories, comment opportunities, and repeated briefings while contaminated material was excavated and shipped away.

U.S. Department of Energy / U.S. Army Corps of Engineers

Chemical guide

Chemicals named in this record

These links explain potential hazards and exposure pathways. A chemical named in a record does not establish that anyone was exposed or harmed.

Chronology

Timeline

  1. 1944–1946

    Approximately 8,000 tons of Linde uranium-ore tailings were stored on the Haist Property.

  2. 1960

    Ashland Oil acquired the property for refinery use.

  3. 1998

    USACE signed the Record of Decision for Ashland 1, Ashland 2, and Seaway Area D.

  4. 2003

    Ashland 1 cleanup was completed after 173,000 tons of material were excavated for off-site disposal.

  5. 2008–present

    The site entered federal long-term stewardship under the Department of Energy Office of Legacy Management.

Environmental record

Documented impacts

  • Stored uranium-processing residues affected soil at the former Ashland refinery property.
  • The material history links Ashland 1 to Linde, Ashland 2, Seaway Area D, and portions of Rattlesnake Creek.
  • FUSRAP eligibility and cleanup criteria address early atomic-energy contamination and should not be used as a blanket description of all refinery-era conditions.

Response

Cleanup and controls

  • USACE excavated approximately 173,000 tons of material from Ashland 1 and shipped it off site for disposal.
  • Related work removed more than 33,000 tons from affected portions of Rattlesnake Creek in 2005.
  • Federal long-term stewardship preserves records and verifies the completed remedy under the land-use assumptions established by the cleanup.

Then and now

The site today

The FUSRAP remedial action is complete and the site is under DOE legacy management. Its present-day story is one of documented removal and stewardship, while the movement of material to Seaway remains a separate containment history.

Atlas connections

Connected places

These collections explain documented material, facility, waterway, ownership, or cleanup relationships. Inclusion does not imply that every place shares one contaminant source or plume.

Radiological-map connection

Place this site in the wider material history

The separate radiological investigation map distinguishes producers, processors, storage, the 100 historical survey records, federal remediation, and current assessment coverage.

Linked research mapOpen the radiological investigation →