cleanup · Erie County

Main & Hertel / The Rails

Buffalo

Former manufacturing and electroplating property cleaned through the Brownfield Cleanup Program and redeveloped as apartments with commercial space.

The documented story

What happened here?

The 4.9-acre Main and Hertel brownfield supported manufacturing beginning around 1910. Products included paint, vehicles, and gasoline pumps, and the Keystone Corporation later used the property for electroplating.

New York's Brownfield Cleanup Program addressed contaminated soil, drums, underground-storage-tank material, transformers, and demolition debris before the property was redeveloped as The Rails, a mixed-use apartment and commercial complex.

Chronology in context

Turning points in the public record

1910 onward

Successive manufacturers produced paint, vehicles, gasoline pumps, and other goods on the property.

Electroplating era

Keystone Corporation conducted electroplating operations, adding a metal-finishing chapter to the site's industrial history.

2024

DEC issued a Brownfield Cleanup Program Certificate of Completion after reviewing the completed remedy.

Present

The property has been redeveloped with apartments and adjoining commercial space.

News record

Major news events

Coverage selected here marks a turning point in public awareness, policy, enforcement, employment, or cleanup. Links open at the original publisher or archive; WNYAtlas does not reproduce restricted articles or images.

Local

A former plating property enters public cleanup review before housing construction

DEC invited comment on the Main and Hertel remedy before the industrial property became The Rails, keeping contamination, vapor protection and controlled residential reuse within one public record.

New York State Department of Environmental Conservation
Local

The remediated site becomes a 312-unit transit-oriented apartment complex

Construction reporting documented the transformation of the underused brownfield beside LaSalle Station while the brownfield remedy supplied the environmental foundation for residential and commercial use.

WKBW

Environmental record

Documented impacts

  • Historic industrial uses contaminated soil and left drums, tanks, transformers, and building material requiring controlled disposal.
  • Electroplating and manufacturing histories guided investigation for metals, petroleum-related compounds, and other industrial contaminants.
  • The brownfield boundary is a defined 4.9-acre cleanup site and should not be expanded to the entire Main–Hertel neighborhood.

Response

Cleanup and controls

  • Approximately 1,700 tons of contaminated soil were excavated and disposed off site.
  • Cleanup also removed about six tons of drums and underground-storage-tank material and roughly 500 tons of building material, including concrete, wood, and transformers.
  • DEC's Certificate of Completion confirms that the approved remedial objectives were met for the site's planned use, subject to any controls recorded in the final engineering documents.

Then and now

The site today

The Rails demonstrates residential and commercial reuse of a former industrial property after state-supervised cleanup. The completion certificate applies to the defined brownfield remedy and does not erase the site's manufacturing history.

School-map connection

See the documented campus relationship

The schools research map explains the documented property, adjacency, or mapped-parcel relationship without treating proximity as evidence of exposure or present school conditions.

Linked schools mapLEWIS J BENNETT HIGH SCHOOL OF INNOVATIVE TECHNOLGY / MIDDLE EARLY COLLEGE HIGH SCHOOL